PROJECT IS COMPLETE

Our big Water Main and Valve Replacement Project is completed.

During this project we installed 11,963 feet of 6-inch water line and 30 6-inch gate valves. One 8-inch and 18 6-inch gate valves were removed. Eight single meter pits, 5 single meter pits with pressure regulators and 23 double meter pits were installed. Fifty-nine 1-inch water service connections were done along with 4 air valve assemblies, 5 flush valve assemblies and 5 fire hydrant assemblies.

3,759 square feet of asphalt concrete pavement patch was done; as was106,000 square feet of double chip seal. The project took 87 days and cost $644,682.90, which was $14,529.10 under the original bid. Lyon County contributed $39,207.84 toward the paving costs.

There were three boil water notices issued, thankfully all sample results came back absent proving that none of the system was compromised, and many days of shut-offs during the installation.

The purpose of this project was two-fold: to prevent future line breaks causing unscheduled repairs and to install more isolation valves for times when water needs to be shut off to various parts of the system.

We would like to thank all of our customers, who's lives were disrupted by this project, for their patience and understanding.

Meetings



NOTICE OF PUBLIC HEARING
February 9, 2012 at 4:15 P.M.

Click here for complete information


A regular meeting is scheduled for February 9th, 4:00 PM at the GID Office

Click here for a copy of the agenda



Minutes of the January 12th meeting

Minutes of the January 31st special meeting

News Letter

Click here

Rates and
    Charges    

Click here

What's in that glass of Quality on Tap

Click here for laboratory analysis




----- 2010 Stagecoach GID quality water report -----
Click here for water test results

Monthly Drawing

The Raffle Winner for November is Les & Ann Dixon. Les & Ann will receive a $50.00 credit on their December bill.

You too can be a lucky winner.

All you have to do is pay your bill on or before the 25th
and you'll be entered in the drawing.

Individual Sewage Disposal System
Regulating Resolution

Click here to see entire Resolution


click here to go to the home page.